ADVERTISEMENT FOR BIDSCapital Projects

Name/Description Water or Sewer Status Design Year Bid Date and results Bid Information awarded Estimated Cost

Estimated Start/completion dates

Scout Master Lift Station Upgrade

06-B8 Sewer

Concept 2010 TBD

Advertisement

Tom Puckett

(513) 785-5370

TBD TBD TBD
LeSourdsville WRF - Expansion Phase I

09-A6

Sewer

In Construction 2009 04/07/09

Advertisement

Steve Seitz

(513) 785-6370

Ameritcon

Rapier Electric

$3,000,000

Summer 2009

Summer 2010

LeSourdsville WRF - Expansion Phase II 05-A4 Sewer In-Design 2010 TBD

Advertisement

Steve Seitz

(513) 785-6370

TBD TBD TBD
West Chester Road Water Main - 2,400 feet of 12" water main. Water In Construction 2009 06/30/09

Advertisement

Wayne Beyerlein

(513) 785-6367

Culy Excavating $418,700

Spring 2009

Spring 2010

Hamilton -Mason Rd to Yankee Rd to (Parallel I-75) - 16" water main extension from Hamilton-Mason to Yankee Rd. (project may be completed with developer project). Water Concept 2010 TBD

Advertisement

Constance Kepner

(513) 785-5134

TBD TBD TBD
LeSourdsville WRF Phase I Improvements - Demolition and Removal Contract - Demolition and removal of various adandoned and unused structures, piping and equipment.

09-A6

Awarded

2009 9/15/09

Advertisement

Steve Seitz

(513) 785-6370

Homrich, Inc. $278,300

Fall 2009

Spring 2010

Liberty Fairfield Water Pump Station Ground Storage Tank Project - Installation of one wire-wound, prestressed concrete water storage tank and appurtenances.

07-C1

Water

Awarded 2009 9/29/09

Advertisement

Steve Seitz

(513) 785-6370

Natgun Corp - General

Rapier Electric - Electrical

$2,900,000

Fall 2009

Fall 2010

Cherrywood Lane Water Main Replacement Project - Installation of 1,110 ft of 6" and 2,225 ft of 8" ductile iron water main and appurtenances.

09-B1

Water

In Construction 2009 9/15/09

Advertisement

Wayne Beyerlein

(513) 785-6367

W.G. Stang, LLC $235,037

Fall 2009

Spring 2010

Route 42 Water Main Replacement - Installation of 962' of 6", 2,292' of 8", 235' of 10", 817' of 12", 4,531' of 16" and 158' of 20" ductile iron water main and appurtenances.

06-B6

Water

On hold 2009 TBD

Advertisement

Wayne Beyerlein

(513) 785-6367

TBD $1,300,000

Spring 2011

Winter 2011

Tylersville Water Main Replacement - Installation of 40' of 6", 125' of 8" and 2,930' of 12" ductile iron water main and appurtenances.

07-C3

Water

On hold 2009 TBD

Advertisement

Wayne Beyerlein

(513) 785-6367

TBD $340,000

Fall 2010

Winter 2010

Hamilton-Mason/ Morris/Dixon Ct Water Main Replacement - Installation of approximately 8,200 linear feet of 12" ductile iron water main on Hamilton-Mason and approximately 3,300 linear feet of 8" ductile iron water main along Morris Rd and Dixon Rd

10-A4

Water

In-Design 2010 TBD

Advertisement

Constance Kepner

(513) 785-5134

TBD TBD

Spring 2010

Winter 2010

Dalewood Subdivision Water Main Replacement - Installation of 5,325' of 6", 8,015' of 8" and 1,400' of 10" ductile iron water main and appurtenances. 10-A3 In-Design 2010 TBD

Advertisement

Wayne Beyerlein

(513) 785-6367

TBD TBD

Spring 2010

Winter 2010